Hi All,

We faced the problem when we upgraded our system to EHP 8 and to do this we also done the upgrade of SAP kernel to 745 PL 200.

We needed to downgrade the system back to 742 as some SQL statements in std and non-std codes started to take much more time.

Good example is MB51 with option Start Off with Material Number, which took minutes for single material number after this.

Anyone faced the same issue with EHP 8 and solved it?

Best Regards,

Tomek

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Aug 15, 2016 at 01:45 PM

    Hi Tomek,

    Please refer "Symptom" section of below SAP Note and the other notes mentioned in same section and see if that matches the issue you faced.

    As per this SAP Note PL201 has replaced PL200 for 745 release

    2299971 - SAP Support Package Stack Kernel 7.45 Patch Level 200




    Thanks,

    Manish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.