Hello All,
In KP26 we have defined one activity. When i am confirming process order and looking for analysis for the same process order, Activity cost is coming drastically different.
For example machine hour activity is maintained rs 100 in KP26 and we confirmed 12 hours for one MT production. The same should be 12*100 = 1200 only. However it is coming around 59000. I don't know why.
Please guide.
Regards,
Sushil
Hi Sushil,
As suggested by ravi is correct and also send me below screen's for cross verification purpose.
Your KP26 and were you are getting 59000 amount that screen short and CR03 with respective cost center and activity combination under costing tab screen.
Regards,
KRK
Hi Sushil,
Check standard value field entered in routing check process below-n
CK13N / CK11N --> QTY Struck- Double click on routing
Double click on operation line
Check value against Activity
Based on formula system multiply standard value with KP26 value. Check with PP to change standard value for correct value.
Regards
Raheem