Dear Gurus,

I'm planning a material through md61 and then I do MRP run. System generates IndReq and DepReq and also planned orders for both. I Firm the planned orders. Then I go back to md61 and add another new quantity on a different date without changing the previous quantities and their dates. Then I do the MRP run again. System generates IndReq, DepReq and planned order for the new quantity BUT also Regenerates planned orders for the quantities for whom planned orders have already been generated in the previous mrp run which I have already firmed.


-What changes are needed to stop the system from creating new planned orders for the quantities and date for which planned orders have already been generated and firmed?

- I even tried by converting firmed planned orders into production orders and then running the mrp on new quantity but system again generated the new planned orders, this time multiplying the quantity by 2. Why is this happening? I have attached screen shot of it. 160 and 180 were the quantities of the first mrp run which I firmed then converted to production order.

Thanks

Shankar

Attachments

MRPMD61.jpg (133.9 kB)