Vendor Eval with multiple Schedule lines and partial deliveries - On time Delivery Performance

271 Views

I'm trying to determine how the GR date is lined up with the Stat date for purposes of calculating On time delivery Performance. I've found articles addressing most of the scenarios but can't find one for the below...

a PO is created with 2 schedule lines with dates 2 weeks apart for 10 each. ( 8/8 and 8/22 for example)

8 units are received on 8/8. I believe these would be applied to the first line leaving 2 open. Variance is 0 because they are on time

1 week later another 8 are received.... does SAP apply 2 to the first line and then the remaining 8 to the second line? meaning 2 would be 1 week late and 6 would be 1 week early? or is it all applied to the second line...meaning 8 units 1 week early?