Skip to Content
author's profile photo Former Member
Former Member

Creation of reorder point for ROH material but practically how will it perform

Hi Expert,

I have created Raw material with VM( Automatic reorder point) in MRP view 1 and also set Reorder point 200 Kg and safety stock as 150 Kg but after issuing the goods ,It is not taking care of safety stock and also How to obtain automatic reorder point in MRP? The stock is still showing below the safety stock and below the reorder point.Please guide me how to run it practically? What is the use of reorder point if it wont work automatically?

Best Regards

Sumit Sinha

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Aug 12, 2016 at 05:38 AM

    Hello Sumit,

    MRP Group 0031 assigned to this material that check if any share of the safety stock used to cover requirements.

    An order proposal will be only created if the the stock level has fallen below the safety stock available for planning.

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Brahmankar ,

      you told that

      MRP Group 0031 assigned to this material that check if any share of the safety stock used to cover requirements.

      But now i changed it and it is still going below minimum safety stock level,If it is happened like this then What is the use to keep minimum stock level in MRP2 view? Please look below screenshot

      pc4.png (26.0 kB)
  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2016 at 07:54 PM

    Hi Sumit

    Check:

    Forecast material master or below

    Regards

    Dimas Faria


    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2016 at 02:37 PM

    Also while running the MRP for FG product in MD02 ,There is no purchase requisition created for ROH material. So why it is required to run MRP for ROH material separately each time?

    Best Regards

    Sumit Sinha

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2016 at 03:24 PM


    pic2.png (18.8 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.