i have a Process Chain for Cube C1 like this:
Start process chain ==> load delta ==> DTP from Datasource to ODS ==> activate ODS ==> delete Index ==> DTP from ODS to Cube C1 ==> create index ==> roll up cube C1 ==> Compress Cube C1.
then i have create Aggregates on Cube for 2 Infoobject: Company Code and Vendor. The Report runs much more faster. My Question is that:
How can i add the Aggregate for these 2 Infoobject in Process Chain?.
i can't find any varian in process chain which automate the Process of Aggregate these Infoobject
Thanks.
Hi,
You created aggregates on info objects which are part of your cube.
so by doing roll up of your cube, those aggregate will be filled.
So nothing to worry about them.