Dear All,
I have an issue with the project PR delivery date. Project material PR is being created having requirement date 31.12.2017. While PR display through ME53N, PR delivery date is getting change and appearing 30.12.2017. I have checked all type calender's there is a holiday (Sunday) on 31.12.2017. While creating a project PR system gives information message also that 31.12.2017 is not working day. But user want to have the PR created with delivery date 31.12.2017 only. I analyzed :
1. Calendar settings cant be changed.
2. Project does not have any kind of WBS date planning and network/activity scheduling.
3. There is no MRP view maintained for that material for planned processing time.
4. GR processing time is also 0 for that material. I even tried to put some GR processing time from 0 to 1 with PR change (ME52N) but delivery date is coming only 30.12.2017.
5. Manual PR is created with the date 31.12.2017 then in PR display system is showing 31.12.2017 date only.
Why this is happening with the project PR then ?
Please help. Awaiting for your respond.
Thanks Indeed.