Capacity is not showing in APO but available in R/3

Hi Experts,

Capacity is available in R/3 for a resource. But it is not showing in APO.

We tried ciffing the resource by deactivating and activating the resource. It didn't help though.

Could you please advice me how to transfer the capacity to apo for a specific Resource.

Thanks,

Ram

1.png (30.7 kB)
2.png (65.7 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Aug 11, 2016 at 09:49 AM

    Hello,

    In ECC work center check the APO resource tab that External Capacity is aactive

    and CFC9 check the setting for Use Ext. Capacity should be set to A when you want to transfer capacity to APO.

    Refer consulting note 674838 - Resource transfer from APO Release 4.0

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.