How to stop the transport imports from QA to PRD in Charm for URGENT change?

594 Views

We would like to disable(temporary ) the transports from QA to PRD in ChaRM for urgent change. And we followed to lock the group in the task list and also in project switch but still via ChaRm we are able to move the transport to Production system.Also we cant disable in LMDB as PRD system is used in other project.

DEV QA PRD


Landscape detials DE1 – QA1 -- PR1 Project Name CHARM1– Only in this project transport should disable from QA to PROD

DE2 – QA2 --PR1 Project Name CHARM2

Note: PR1 is used in CHARM2 project as well so we don’t want to disable the transports from QA2 to PR1.

Please let me know?