Dear PP Experts
Can I have any Control Key on operation in routing in order to have below behavior?
0010 OperationA
0020 OperationB
0030 OperationC (milestone)
Now what I would like to have is that if I confirm operation 0030 then co11n confirms operation 0030 & 0010 but avoid 0020. Until and unless I specifically enter 0020 on co11n to confirm this operation only then it should be confirmed. Since milestone operation behavior confirms all operations above it so I cant segregate materials. I have 0020 operation which is performed only when it is required.