Skip to Content

Process chain asks for transport request while scheduling/activating.

I had made changes to a process chain and saved it to a transport.After it moved to test system, we are seeing that for scheduling / activating the process chain, it asks for a transport request. it was not the case earlier. I even checked the scc4 setting/ object changeability setting. Its all fine still asks for a customizing TR.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Aug 10, 2016 at 08:32 AM

    Try this,

    RSA1 > Transport Connection > Object Changeability > Select RSPT, RSPV RSPC Types and click to make "everything changeable".

    see this for more details.

    Defining Object Changeability - Generic Tools and Services - SAP Library

    Thanks,

    Bhavin Vyas

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 10, 2016 at 09:00 AM

    Hi,

    Is this is happening for only process chain or any other objects as well.

    please try to change full info pack selections and save.

    whether it asked TR or not.

    if its asking for TR then seek basis team help to change those settings.

    Thanks.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.