on 08-10-2016 5:35 AM
Hello Satish,
Please make relevancy indicator in the work center against each activity type
then reread the master data in the production order.. system will read the activities from the work center to Routing same can be copied to Production order
Regards,
Venkatesh..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
operation timings means set up time and processing time of a n operation in operation overview of production order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
IF you are using the standard formula SAP006, than this might not be calculating the Processing time as the "Allowed for scheduling" is not there in OPKM transaction. This might be the reason.
Try to use SAP002 and assign the same in the scheduling view of the work center also.
Regards
SS
Satish,
The work center which production order is having 17070101 and the latest screen you are showing as 17070500
So please ensure the Routing data whether you are using the proper work center or not..
if your work center is correct then check in routing operation details whether activity types has been updated from work center or not
if these activities have not updated then make relevancy Tick mark in the Work center--> Costing Tab-->Relevancy tick mark active for all activity types
Regards,
Venkatesh..