Skip to Content
0
Former Member
Aug 09, 2016 at 05:59 PM

Closing Inspection Lots

904 Views

So production TECO's an order when they decide they don't have the sufficient resources. They TECO they can't cancel a production order once it's released. They change quantity to 1 or 0 then TECO it out. The problem is that it leaves an open inspection lot every time they do that and there's no way for quality to close them all out without manually going in SAP and individually closing them out.. Is there a way to cancel an order completely so that there is no open inspection lot or production order left?

Let me know if you have questions. I'm still learning the system myself