Dear Gurus,
When I run MPS (MD40), at plant level, it doesn´t create planned orders for the material.
However if I run MPS only for the material (MD41) it works fine. The system creates planned orders.
MRP type is M0
Lot size is EX
Strategy group is 40 and the necessity type is VSF.
Why MD40 doesn´t work but MD41 does?