Hi ,
How i am Working rough cut capacity planning
---------------------------------------------------------------------------------------------------------------------------------------------------
I seen in scn threads.
In OP45 , pls ensure that for the usage,task list type 3 (Rough cut planning profile) is included is only required confiuration setting.
1- Create Rough cut planning profile - MC35. Enter material and plant nd execute. Enter status = 4, usage = 1.
Enter a resource name and double clik on that line, choose Example work centre: Enter work center name, plant and unit = H.
Enter the times required in Hours in the time buckets and save
2-Create SOP plan - MC87. Enter material and plant. Execute. Enter sales and prod qty. Go to views>Capacity situation>Rough cut planning>show.
3.In mc82, go to views->capacity situation->show
You could display the capacity requirements at the bottom of the screen.
-----------------------------------------------------------------------------------------------------------------------------------------------------
In the Rough cut planning i created planning profile. But in SOP i cant see the rough cut planning (But it is in GRADOUT)
Please Guide me how to come over from this issue
Thanks & Regards,
LEO