Dear all,

Please Provide your inputs regarding the information message "there is no classification for batch" at the time of the Process order saving.

thanks in advance. Message No : VL855

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Aug 09, 2016 at 05:36 AM

    Hello,

    Please check the scheduling profile assigned in work scheduling view of your material master.

    Check it's config for bath classification in CORY under Batch management.

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 09, 2016 at 06:41 AM

    Dear,

    As suggested Brahmakar check CORY settings and check the material master classification view whether Batch class is maintained or not.

    Thanks,

    Naresh.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.