Reliability Maintenance Strategy

Hi,

Is it possible to map the requirement of Reliability Strategy Maintenance in SAP?

Reliability Maintenance Strategy consist of four pillars:

  • Inspection -> Predictive Scheduled Maintenance Plan
  • Planning -> Manual Scheduling of Predictive Notification generated against any NCR found from Inspection Order Operation Confirmation.
  • Execution -> Converting of above Notification to Order and closing till confirmation and TECO and generate if any NCR found while Order Operation confirmation.
  • Improvement -> If any multiple re-occurrence of same NCR against same equipment if found, then an Order is created by a Special Task Group maintenance team to overcome issue to resolve it through Quality Circle Process.

I have tried to map the above requirement by doing following steps:

  • Inspection -> Scheduled Maintenance Plan Predictive Type order.
  • Planning -> Backend enhancement done in IW48 & IW41 using user exit to automatically generate notification against any NCR found while doing work confirmation.
  • Execution -> Its a normal process.
  • Improvement -> A unique of order type provided.

Things I am unable to do is:

  • Linkage between the new notification generated and the previous work confirmation no.

Please guide how to over come the requirement or guide if any other process I need to follow to meet the whole end to end requirement.

Regards,

Fazal

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 10, 2016 at 01:29 PM

    Hi Fazie,

    PM was created if basing on the bases of Reliability Maintenance Strategy

    In the confirmation of an order, you can open a new notification, and it can put in this notification the order number (it can be a text field, or you can configure a new field)

    Regards

    Dimas Faria


    pastedImage_0.png (42.1 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 11, 2016 at 04:23 AM

    Fazal

    Are you talking about RCM?

    Regards

    Savas

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 11, 2016 at 05:41 AM

    Hi Fazle,

    From previous work confirmation you can create notification and this you can use as reference while you are generating new notification for the purpose of mapping improvement through unique order type.

    Regards,

    PS R


    n1.png (9.3 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.