Former Member
Aug 05, 2016 at 12:15 PM

Formula in Wc

106 Views

Dear Friends,

I am a CO consultant and working on an issue related to costing of an activity type and need your guidance on setting up the correct formula in work center. We do not have PP resources to help in this issue which may seem very basic for PP experts.

I have gone thru the below link to model my design but for some reason could not get the desired results.

Work Center Formula and Overhead Calculation

Anyways here is what I am trying to achieve;

Variable Activity price is set as 1 in KP26 for 1000 units with the activity type UOM as EA

I want the cost to be as follows:

Operation quantity / Base quantity * activity price

where operation qty = Production order qty

Base qty = routing base qty ( which is same as our costing lot size)

I have tried to use SAP standard formul's SAP001/ SAP0002/ SAP006 ( ofcourse with UOM changed to Time units) but unable to get the correct result in costing.

Here is an example for your perusal:

Base qty = 1000 EA

Operation qty = 1200 EA

Activity cost should be = 12

Could you please help me on how the work center and routing should be set up to get the above result?

Thanks for your help in advance.

Vamsi