Skip to Content
0
Former Member
Aug 05, 2016 at 03:10 AM

0UCCONTRACT Data Do not reconcile with ISU Extracted DSO

60 Views

Hello All,

We are having an issue related to time slice data in 0UCCONTRACT in SAP BW on HANA. When a contract get a move out date updated it should take the same in the Valid TO column date as its in DSO and EVERH table in SAP ISU side.

But while transferring data in 0UCCCONTRACT Master data object in SAP BW HANA from DSO (Utility Contract - Time-Independent Attributes), its not getting populated. Below is the scenario explained.

We are aware that the normal behavior of the master data is to create time slice of 01.01.1000 and 31.12.9999 .

The issue is that it’s not creating a new time slice where it should.

Currently in BW on HANA (PH1) system –

Contract

Valid From

Valid To

30015090

01.01.1000

16.07.2009

30015090

17.07.2009

31.12.9999

In Source system – also in DSO we have below dates arriving after a contract gets it move out date ( Valid date ).

So, we expect the below time slice in BW for this –

Contract

Valid From

Valid To

30015090

01.01.1000

16.07.2009

30015090

17.07.2009

31.05.2016

30015090

01.06.2016

31.12.9999

As you can see here that the middle timeslice has not been created in the master data in BW side while updating the date from DSO.

What is missing I am really not sure, but I was just looking if someone has handled such scenario in past or any clue what we are doing wrong ? I have raised the same with SAP as well , but no answers yet.

Many thanks

Yash