Aug 04, 2016 at 07:43 PM

Start Date and Avail req date in product view are same

66 Views

Hello All

I would need some help and info here

I have process order created in ECC at 8/5, the material has consumption mode 2 (BW and FW cons) and planning time fence as 7 days, but in APO product view my start and avail date as 8/13, usually we will see start date as 8/5 and avail date as 8/12. Due to this we are not able to confirm STO and we are creating dummy STO to look like production available.

But we also have a Process order created for 8/6 in ECC and our product view in APO shows correctly as start as 8/6 and avail date as 8/14

Please help with what is wrong and I have attached the screen shot of the two PO in ECC and Product view.