I have got the customer requirement like "MRP should not consider the requirements(Service orders, STO, Sales orders, Reservations..etc.) for generating the PRs if these requirements are created before particular days say 60.

I have checked the planning horizon but I believe it is used for planned independent requirements to restrict the requirements entered for future dates.

Currently MRP is implemented for various types like PD, P1, P2.. etc and above filter/check/condition should work for all such scenarios without disturbing existing set-up of MRP.

I am also exploring the way out BAdI & Method: IF_EX_MD_CHANGE_MRP_DATA CHANGE_MDPSX_EBAN but I am not sure how to flow in the requirement dates of components into this method and how to build logic for filtering.

Any standard or custom way out to implement this requirement?