I have problem with settings of planning periods in MD26; Planning calendar exists and I need to extend it. After periods calculation I have following situation: calendar is "Only Mondays" if day is not-working day , previous day is selected; so periods should be set for example :

29.08.2016 - 04.09.2016

05.09.2016 - 11.09.2016

etc.

problem is that after Enter or Save, system automatically change date from 04.09.2016 to 01.09.2016 and 05.09.2016 to 02.09.2016

I have such situation for some periods. Based on what system makes this change? I am confuse really.