Dear seniors,
We have backward scheduling based on the Basic End Date in the Planned Order (PLO).
IF the Schedule Start Date falls in the past, it will perform forward scheduling and a new Schedule End Date is proposed, in the future.
The issue I have is that the Schedule End Date is now in the future of Basic End Date. And based on the basic end date, Sales Orders are confirmed to a customer.
Example:
Basic End Date 05'th of August
Schedule End Date 10'th of August
The customer knows that the goods will be done in 05 based on PLO info, when they are actually finished only in the 10'th of August
Please let me know if there is setting to make the Basic End Date follow the Scheduled End Date
Thank you
Alex