Hello Experts!
I need to include 3 new activity types in Process Order Confirmations:
AS120 - Energy
AS130 - Depreciation
AS140 - Others
This New activity types will have to "read" (replicated) the hours from the existing acitiviy Type AS110 - Machine Hours.
I Already assigned them to the Resources in CRC2.
What are the next steps to configure?
I need to confirm them in COR6N, and if I change the hours from the planned hours displayed, I need them to automatically derive from AS110.
Can you help me?
Kind Regards
Mayumi