Hi Experts
In MD62 PIRs are entered as weekly demand. In CM01 I selected the daily view option of the capacity load in hours. Although the available capacity is 50 hours everyday MRP run scheduled on each day as 42,42,44,50,50 . How is the logic of this split happening in CM01. Why it is not scheduled as
50,50,50,50,28 first to the full capacity each day and remaining requirement on last day.
Thanks
Sakthi