Hi SAP Folks,
Labor cost is not coming in Planned cost in maintenance order. I have check mostly thinks but not able to get success. Actual cost comes after the order confirmation,what ever I defined in activity KP26.
But I want to see the Plan cost of activity in cost tab.
Configuration points:-
1) CstgVariantPlan has assigned
2) CstgVariantActl has assigned
3) RA Key has assigned
4) Costing sheet
Please suggest your opinion. How can I get this
Thanks
Regards
Gaurav Solanki
Hi,
I got the solution.Thanks for your efforts.
Regards
Gaurav Solanki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Gaurav
Can you send us a screen-shot of the Control and Operations tab of the maintenance order please.
.
Also ensure you tag the following so you get a better response: PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Gaurav Solanki,
Questions:
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.