Component Batch Availability

143 Views

Situation:

  • Planned order generated for HALB via MRP for future date.
  • Planned order converted to process order. Basic and scheduling dates on process order reflect the future dates from planned order.
  • HALB process order is released, confirmed, TECO'ed, settled on current date (prior to dates specified on order). Stock for HALB batch is available in inventory. Goods receipt document reflects actual current posting date.
  • Process order created for FERT for which HALB is component.
  • Availability check for HALB component shows the batch's inventory as not available, unless the FERT process order's start date is moved to the future (past the HALB process order completion date.) HALB batch stock cannot be shown as available on current date, even though it was posted to stock in the past, because its planned/process order was scheduled for the future.

Is there a way to have component ATP look at current stock, posted on/before current date, if its original planned/process order was dated in the future?

Alternatively, can the dates be automatically adjusted to the present when converting a future-dated planned order to a process order?

Thanks and regards.