on 08-01-2016 2:47 PM
Hello Experts,
During the cancellation of the production confirmation through transaction MF12, i am getting the below error message
Message No. RU008 - No operations exist under order XX.
After analysis we found that, costing estimate updated after production confirmation which may be the reason behind this issue. After going through various threads, i found that SAP Note 1013857 needs to be implemented to handle such issues.
But as i checked, this is already implemented in our system (ECC 6.0 - SAP package SAPKH60510) even though system is not allowing to reverse the material document.
Request your kind inputs on this.
Thanks,
Mahesh
Hello Mahesh,
Could you please try the confirmation cancellation through MF41..
Similarly ensure the planned order which you are doing the confirmation cancellation has the operation in the detailed scheduling tab..
Regards,
Venkatesh..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please refer Sap Note 449738 or 553578 and see if these can help
453847 - Error message RU008 with confirmation of operations
449738 - Error message RU008 w/ backflush of operations
Thanks & Regards
Sandeep Kumar Praharaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.