Skip to Content
0

actual cost not getting in sap ps for material procured

Feb 09, 2017 at 06:36 AM

67

avatar image
Former Member

I'm doing capex project, with valuated project stock. I'm procuring material (stock material) for my project with item category "L".

PR is getting created (PReq + Res - WBS elem.).

MM guy has completed purchase cycle (Acct *** category "Q").

He has done GR, invoice verification. FICO has made payment.

But I'm not getting this actual cost in PS

What could be the reason?

Please give me possible solution.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member Feb 09, 2017 at 07:53 AM
0

Hi Ashutosh,

1st of all, how do you know that actual cost is not captured in PS, i mean it is not getting updated in table or it is not showing up in reports?

>1st check whether it is updated in RPSCO table or not.

>check the valuation class and consumption G/L is correct or not.

>Whether cost element exists for that G/L.

>If cost element exists,check whether it is maintained in the PS value category

If still problem persists then please share some screenshots

With Regards,

SR

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Mar 15, 2017 at 07:09 PM
0

Hi Ashutosh,

you should do GI now.

Share