actual cost not getting in sap ps for material procured

Former Member
0 Kudos

I'm doing capex project, with valuated project stock. I'm procuring material (stock material) for my project with item category "L".

PR is getting created (PReq + Res - WBS elem.).

MM guy has completed purchase cycle (Acct *** category "Q").

He has done GR, invoice verification. FICO has made payment.

But I'm not getting this actual cost in PS

What could be the reason?

Please give me possible solution.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Ashutosh,

you should do GI now.

soubhagya_rout
Participant
0 Kudos

Hi Ashutosh,

1st of all, how do you know that actual cost is not captured in PS, i mean it is not getting updated in table or it is not showing up in reports?

>1st check whether it is updated in RPSCO table or not.

>check the valuation class and consumption G/L is correct or not.

>Whether cost element exists for that G/L.

>If cost element exists,check whether it is maintained in the PS value category

If still problem persists then please share some screenshots

With Regards,

SR