actual cost not getting in sap ps for material procured

I'm doing capex project, with valuated project stock. I'm procuring material (stock material) for my project with item category "L".

PR is getting created (PReq + Res - WBS elem.).

MM guy has completed purchase cycle (Acct *** category "Q").

He has done GR, invoice verification. FICO has made payment.

But I'm not getting this actual cost in PS

What could be the reason?

Please give me possible solution.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Feb 09, 2017 at 07:53 AM

    Hi Ashutosh,

    1st of all, how do you know that actual cost is not captured in PS, i mean it is not getting updated in table or it is not showing up in reports?

    >1st check whether it is updated in RPSCO table or not.

    >check the valuation class and consumption G/L is correct or not.

    >Whether cost element exists for that G/L.

    >If cost element exists,check whether it is maintained in the PS value category

    If still problem persists then please share some screenshots

    With Regards,

    SR

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 15, 2017 at 07:09 PM

    Hi Ashutosh,

    you should do GI now.