Hi experts,
I had to extend the MATMAS IDoc with a field, which is being set in the classification of a material in material master with MM01/MM02.
Saving of the classification field value to the material works fine. But no MATMAS IDoc is being triggered when adding/changing this classification field.
I have seen some threads in the internet how to activate change pointers on classification fields, but I can't Activate change documents for the material class, like it's described here:
Activate change documents - Product Lifecycle Management - SCN Wiki
This would have huge consequences for other areas in the company.
I thought about, if I could trigger the change run for classification changes in an user exit, which is called while saving the material in MM01/MM02. Does anybody know, if this is possible and knows how to do this?
Thank you & best regards,
Michael