Hi experts,
Below is my BOM structure
Header:
FINISHED -1 has below bill of materials
2nd level
SEMIFINISH ASSEMBLY -1 no
ROH1 – 1 no
3rd level
ROH2 – 1 no
ROH3 – 1 no
If I now run MRP for FINISHED material only, I see that planned orders are created for both FINISHED (primary demand as PIRs exist only
for FINISHED) and also for SEMIFINISH ASSEMBLY (dependent requirements comes from FINISHED)
Although MRP run for FINISHED creates dependent requirements also for ROH1, ROH2 & ROH3, why the planned orders are not created for ROH1,
ROH2 & ROH3?
Should I run MRP separately for ROH1, ROH2 & ROH3 separately?
The whole scenario is for MTS (strategy -10). I maintained strategy -10 for both FINISHED & SEMIFINISH ASSEMBLY. Should I maintain
strategy -10 also for ROH1, ROH2 & ROH3 or not needed for these 3?
Thanks
Sakthi