E Stock exclude from MRP

Dear Gurus,

I set a storage location excluded from MRP, and it's functional for un-restricted stock. But after I use MIGO 412 E to transfer the un-restricted stock to E-Stock, the E stock was involved in MRP calculation. Is this the standard function? If so, how can I make this E stock excluded from MRP ?

BR,

Sivan

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jul 28, 2016 at 08:43 AM

    Hello,

    Refer SAP KBA 1935015 - Exclusion of storage locations from MRP doesn't work for project/sales order stock


    The system is working correctly in this case. It is standard design due to technical limitations:

    Individual stock segments (like project stock and sales order stock) are separated from plant stock. So MRP cannot put together their quantities and plan them as a single stock. This has always been the standard behaviour. The excluded storage location is a stock segment and the WBS/sales order is a stock segment. It is not possible to assign two different segments for the same MRP Element.

    Therefore, the excluded storage location with project stock/slaes order stock is not supported in SAP. The "SLoc MRP indicator" field in the MRP4 view of material master can only be used to exclude storage locations from MRP at plant level (net requirements planning).

    You can use the BADI MD_CHANGE_MRP_DATA to exclude special stock from MRP.

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 28, 2016 at 07:35 AM

    Hi Sivan

    In MRP run we can exclude Blocked Stock, Stock In Transfer, Restricted Use and Store location.

    Please check with Collective/Individual Indicator 2 in MRP 4 view.

    Regards

    Suresh.M

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 28, 2016 at 08:20 AM

    Hi Sivan,

    I believe its Make to Order Scenario.

    As "E" stock is special stock Indicator which is linked to specific sales order also In material master if you keep Availability check indicator as 2 it means Sales order will participate in MRP run.

    So that is the reason why MRP considering that stock.

    1. Material Master availability field

    2. Strategy group

    3. SPRO path to Exclude storage location.

    Regards,

    Prasad Joshi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.