on 07-28-2016 6:51 AM
Dear Seniors,
We have a situation in which the number of splits in the routing operation is set as equal to the Number of individual capacities in the Work Center.
Please let me know if there is a way of linking the two, so that if the individual capacities are changing in the work center, the number of splits will automatically update in the routing operation.
Many thanks,
Alex
Hello,
As I know this is not possible in standard SAP, and there is no tool to update number of splits in routing as per the work center.
One work center can be used in different routing so it is not necessary to have that all the products required splits.
You have to manually update the number of split in routing, you may create query for routing and work center to compare the number of individual capacities of work center and number of splits routing. If any mismatch adjust them manually.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Many thanks for your input Brahmankar.
I have done a test with the "Required Splitting" check turned on in the routing.
The system is able to pick the number of individual capacities from the Work Center.
Anyway, rescheduling the orders is necessary all the time after the number of individual capacities is changing.
I always appreciate your input, many thanks again
Alex