Multi Activity resource - Number of Individual Capacities- CTM

522 Views

Hello,

We are using certain work centers with No. of Individual capacity > 1 and these work centers are mapped in APO as Multi Activity. We are using CTM - Continuous planning, with source of supply as PP/DS.

In the Resource master in APO, the start and end times are maintained with no breaks and 100% utilization. Productive time and number of capacity is mapped from ECC.

Example

In PDS , the Operation 01 - Resource consumption (V) - 10 hours (converted from seconds)

Demand - 50

Productive time - 24 hours

Number of Capacities - 6

Order scheduled with CTM - 50*10/24 ~ 21 days ( assuming 7 days calendar). << Duration between start and end of the CTM order is 21 days>>

Expectation is Order should be scheduled - 50*10/(24*6) ~ 3.5 days . This is considering the Number of Capacities and Total capacity - 24*6

Question: Is the Number of Ind. Capacity considered in CTM when using Multi Activity resource or just the Productive time is considered?

Thanks,

Tejinder Gupta