Dear Experts,
I have requirement, I have work center with 3 shifts and 3 breaks, I have configured breaks and shift sequence through T-Code OP4A and configured order type to allow scheduling and breaks, then I have assigned the shift group to the work center.
When I Create a Maintenance order and assign that work center and schedule the maintenance order, the work center only checks for the first shift only, also if a maintenance order have an operation with time that's exceed the shift, the scheduling moves it to the next day without take the other shifts inconsideration.
Any ideas.
Thanks.