Dear Experts,
Here is my requirement, I have one structure for shutdown which is activity wise and my budget controlling on department level line Mech, ElE, Civil etc.
not on activity level Now if i am creating department wise WBS and dividing activities among them so might be possible one activity come in multiple WBS but my scheduling structure is different so is there any way we can select desire structure from existing for creating Bar chart ?
Example- WBS MECH Scheduling structure
Activity A Activity A
Activity B Activity B
Activity C Activity C
Activity D
WBS ELE Activity E
Activity D Activity F
Activity E Activity G
Activity A
WBS Civil
Activity F
Activity B
Activity G
Thank You,
Regards,
Yogesh Acharya