VAS Work center is not getting determined for VAS order

Hello,

I had created a VAS inbound scenario, where VAS work center is not populated in VAS order. So that i am unable to perform VAS step in inbound. Plz tell me what i have missed.

Where as I have maintained VAS work center as

In POSC, I have maintained the VAS step

inb1.PNG (13.5 kB)
vas1.PNG (21.0 kB)
vas2.PNG (15.3 kB)
vas3.PNG (18.3 kB)
Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 26, 2016 at 04:45 AM

    Hi Srikanth,

    Check your work centre configurations in EWM->master data->Work Centre, see if you have assigned step AVS1 to your work centre or not. Step also need to be linked to work centre. Also link your bin with your work centre in easy access in Define Work Centre Attributes.

    Regards

    Anoop S

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 26, 2016 at 11:33 AM

    Hi Srikanth,

    Did you maintain the external step 'AVS1' in the packaging specification under 'warehouse ' tab?

    BR,

    C K Reddy