Hello Experts
At present we run optimiser in 2 versions (Active 000 and another simulation version 002) with different capacities in SEQUENCE.
Each optimiser run takes 5 hours time, so after 10 hours we are only analyse results.
Business team want result faster. So we are exploring to run both optimiser run in 000 and 002 in PARALLEL.
We tried this parallel run but it one got failed with error message'Maximum number of users for server module SNP exceeded'.
I checked TCP/IP connection in SM59. RFC connection for SNP optimiser server is maintained as OPTSERVER_SNP01.
Also checked RCCF:Destination for Engines in SPRO. Destination ID SNP01 for SNP Optimiser is there with communication connection as OPTSERVER_SNP01.
How can I able to run optimiser for both 000 and 002 version in Parallel?
What is the possible steps to increase number of users for server module SNP?
Please advice.
Thanks
Pradipta Sahoo