Dear experts,
We are using scale price and we want the adjust the blocks (scales) when the billing period is diffenrent from a basic time (30 days). Time adjustment is available in block price but unfortunetly not available for scale price.
Example:
Quantity 8, billing period : 15 days, basic time for blocks: 30 days
Block 1 : from 0 to 10 --> price 1$
Block 2 : from 11 to 20 --> price 2$
During billing, result should be 16$ but the system is calculating 8$.
Is there any option to make the blocks (scales) time adjusted?
Thanks & Regards.