Project commitment at PO release and GI

Dear All,

Can anyone tell me is it possible to show commitment amount from budget for a project once PO is released and GI is perform for material instead of PR creation level and reservation showing commitment amount.

As I have seen on SAP standard, commitment shows at PR and reservation level.

Regards,

Faizan

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

5 Answers

  • Best Answer
    Posted on Jul 25, 2016 at 04:53 AM

    Hi Faizal,

    you can use t codes CJI3 and CJI5

    thanks

    Jaidev

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 22, 2016 at 08:34 AM

    Hello Faizan -

    Commitments are coming from Reservations, Purchase requisitions, Purchase orders. Initially commitment are shown as PR, once PO is created that would PR is not shown as a open commitment.

    Again once GR is completed, commitment amount is reduced wrt quantities received into stock.

    Please try to provide specific details if you are looking for something else.

    thanks

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Somash,

      I have created an activity on which PR is raised and due to this my budget is committed so if partial PO is created than what amount will be reflecting on commitment field in report?

      Regards,

      Faizan

  • author's profile photo Former Member
    Former Member
    Posted on Jul 22, 2016 at 09:14 AM

    Dear Faizan,

    There is no standard reports available in PS which will show you commitment value after GI is done. Commitment value get reduced as soon the GI is done.

    Now if still you want to see the Commitment value for PR/PO you need to Develop report while fetch value from COOI:ORGWTH for Local currency and COOI:ORGWTK for CO Area Currency.

    Regards,

    Omkar Deshpande

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 25, 2016 at 12:35 AM

    Hello Faizan,
    Both PR and PO will consume commitment, but they are with different value types.
    PR commitment is with value type(WRTTP) 21, while PO commitment has value type 22.
    You can see if you could use the different value types to distinguish PR and PO commitment.
    Best regards,
    Miya

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 25, 2016 at 04:11 AM

    Hi Faizan,

    Basically commitment comes from PR and PO too. but when you make GR/GI commitment will reduce will convert into actual cost.

    Now you want to see customise data on same screen which is not possible by any one of the standard report so you have to go for customise report with the help of abap.

    Meanwhile you can see the commitment for project by CJI5.

    Regards,

    Sanjeev

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.