on 07-21-2016 10:02 PM
Hello, we have agreed to a 90 day stocking level with our customer of 300,000 units. How can I configure MRP in the material master to reorder at 100,000 units and replenish to a maximum stock level of 300,000? Currently, I am using an annualized forecast and PD strategy but it is creating planned orders for each month. Our intention is to produce the material approximately once every 3 months.
Cheers,
Justin
Hi Justin
The customizing transaction to create lot sizing procedures is OMI4.
You can create a new lot sizing procedure as a copy of MB, changing the number of periods to 3.
If you want to reorder at 100000 units, you should use a reorder point MRP type, such as VB.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Many thanks Caetano!
Unfortunately I do not have direct access to OMI4 and getting anything custom is difficult to obtain at this time. I am wary to use the reorder point strategy as I want to use a forecast to drive planned orders that will create demand for the raw materials (in this scenario the lead time of raw materials is longer than the lead time of the finished good).
My thought is to use a forecast with cumulative demand entered only every 3rd month but this seems like a work around rather than using the system as intended.
hai jayadeep,
That I know but i need to know like how you will find (OR) calculate the RE-order Point and Safety stock.
Take a example
Re-point will calculate by adding PR to PO creation time + Vendor delivery time + Safety stock
My question is ho you will get the data in sap to create Re-order point, I know that in material master MRP 1 We have option to enter RE-order point (for Manual reorder point)
But that quanty how you will calculate
Hi Justin,
As you want to configure MRP in material master to reorder point and maximum stock level and additionally expecting forecast to drive planned orders to create demand for ROH material but in the Reorder point Strategy forecast/ planned independent requirement will not consider in net requirement calculation.
Kindly check below link for more details.
Could you please let us know the business scenario like MTO /MTS ? For Cumulative planned order for 3 months , lot size config as suggest by Mr. Caetano is the best option also just refer below link. I hope it will work for you.
I will revert back to you if I have found any other solution.
Requirements generated by future demand are cum... | SCN
Best Regards,
Prasad J.
Hi Justin,
please use MRP type as VB-reorder point planning and
HB-replenish up to maximum stock level.
Here 2 calculation will act for determining requirement
formula1 -based on Maximum stock level (in your case 300,000)
Maximum stock level-plant stock-existing fixed receipts=lot size
300,000-100,000-0=200,000 (quantity as per formula 1)
formula2-based on reorder point
Reorder point + total requirement-plant stock-existing fixed receipts=lot size
100,000+300,000-100,000-0=300,000 (quantity as per formula 2)
Now you can choose if you only want Maximum stock level to be considered then do not consider external requirements for MRP in this case only formula 1 will be used which will give you quantity not more than maximum stock level.
Also if stock falls below reorder point then system will create requirement for shortfall quantity.
formula 2 will be applicable if external requirements are taken into consideration for MRP.
in this system creates proposal by comparing both the formulas and quantity which is greater will be used for order proposal.
for your case do not consider external requirements into consideration so always quantity as per formula 1 will be calculated for order proposal..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
see below example
if plant stock is 50,000
reorder point-100,000
Maximum stock level-300,000
Now planning file entry will be created as plant stock is less than reorder point.
when MRP run will be done system will create order proposal
Maximum stock level-plant stock-existing fixed receipts=lot size
300,000 minus 50,000 minus 0=250,000 units
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.