Former Member
0 Kudos

Dear friends,

While run the mrp system will generated the planned orders.Whatever the master bom and routing will be copied in to the planned order.Now they don't want convert to production order. After some days they want to convert to production order in mass.

In between they will chage bom and routing.So they want latest bom and lates routing while conevert the planned order to production order when ever they want.

I told click read pp master data .they asked so many orders are there. it is very difficult.So please guide me how to develpo this requirement.

Regards,

Anitha

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Dear Ani,

For your requirements, SAP has the note: 391846.

Please refer this SAP note. If you implement this SAP note, then in the Production order order type dependent parameters (OPL8) you will be able to see there is an additional option "BOM explosion when converting planned order". In that input you can select the option either 1 or 2 depend upon the scenario. This will help in re-read the master data automatically while converting the planned order to production order. So this is specific to Plant and order type, so whichever plant and order type require this functionality you can maintain this setting in OPL8.

I hope this will help you.

Thanks,

R.Loganathan

former_member202646
Participant
0 Kudos

Dear Loganathan,

Thank you so much for your valuable input. I have a doubt and I will be thankful if you can guide me on that. The above note is for exploding BOM at the time of planned order to production order conversion but I want to read routing data also. Can you guide me in this?

Best Regards

Senthil Nathan Karunanithi

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

As of Release SAP_APPL 6.17 (Support Package SAPKH61705), the function implemented by the modification note 391846 is available in the standard (see SAP Note 2011198).

Best regards

Caetano Almeida

Former Member
0 Kudos

Dear Senthil,

Though it says "BOM Explosion" both the BOM and Routing (Read Master data) will be re-exploded when selecting this option in OPL8.

We have implemented this for one of our client, 3 to 4 years back. And I do see both the BOM and Routing is re-exploded while converting planned order.

Thanks,

R.Loganathan

Former Member
0 Kudos

Dear Ani,

Did you had a chance to check the SAP Note and activate it for your requirements?

Thanks,

R.Loganathan

0 Kudos

This message was moderated.

former_member202646
Participant
0 Kudos

Dear Ani,

Please run MRP again by keeping the planning mode as 2 (Re-explode BOM & Routing)

It will adjust the existing planned orders with the latest changes made in the BOM & Routing.

Best Regards

Senthil Nathan Karunanithi

prasad_joshi8
Explorer
0 Kudos

Hi Ani,

To convert Planned orders in to production orders in mass with latest BOM & routing, MRP Run can be a good option but you need to delete existing planned order first.

Also find below link for similar Thread

Update BOM Changes in Planned order and product... | SCN

Regards,

Prasad J.

sandeep_praharaj
Contributor
0 Kudos

Hi,

  In that case you can advise them by rerun the MRP by choosing the reexplode Bom & routing option so that planned order will update with latest routing & Bom.

Thanks & Regards

Sandeep Kumar Praharaj