Hello Experts,
While converting the planner order to Process order through MD04, wrong quantities of components are getting calculated.
MD04 screen shot with highlighted planned order.
Planned order Component view screen. Quantity is as per BOM.
BOM screen with 4608 Kg of Quantity.
Now you can see the BOM qty is matching to Planned order component view quantity which is perfectly fine.
But see, the process order screen which is fetching quantities not from BOM.
Please guide from where wrong quantities are getting fetched.
Best regards