network order requirements is not showing in MD04 screen

Hi Team,

Good Day!

below is the issue:

PIRs created for material(XXXX) and the strategy is 70(Planning at Assembly Level).

Network order created for above material(XXXX) against the WBS element.we are unable to see the requirements in MD04 screen.

can someone help me how the PIR will be consumed in this scenario(behavior of the material) and let me know if you need more information.

i would also like to understand the behavior of the network orders with this strategy.

Your Cooperation in this regard would be highly appreciated.!


Thanks & Regards,

Sailendra Mulagada

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jul 20, 2016 at 08:28 AM

    Hi Sailendra

    Please use mixed MRP as 1 in Material Master MRP3 view for the Strategy Group 70.

    For better understanding on Planning Strategy 70 please go through the below link.

    https://help.sap.com/saphelp_erp60_sp/helpdata/en/42/23bf53d25ab64ce10000000a174cb4/content.htm

    if you are not not clear please come back.

    Regards

    Suresh.M

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.