Hi all
I'm planning work in PM order,
In the activity tab I entered planned work + activity type but i cant see the planned cost from this work.
I do see it after the work is cinfirmed - in the actual costs.
I will add that when I assign material I do see planned costs and after the good issue it goes to actual costs.
Is there some customization i missed?
Regards,
Irit