Hi,
I have a product which has a child part level BOM. Now there is a running change in the product which affects some old child parts replaced by new one having different part numbers.
Old parts to be used in assembly and production till stock is consumed but all further ordering should be as per new BOM having new parts.
This means we need two BOM , one for manufacturing till stock of old parts is consumed and one BOM for further planning and ordering.
If we use old BOM then with each MRP run the shortage is generated with OLD parts and also schedule to vendors.
In other case if we change the BOm with New parts then old parts can not be used.
Pl help with the solution.
Sunil Verma