Manual recognize revenues

Dear all,

We are currently implementing SAP ByD in our company and we are facing a problem with the revenue recognition. We are deploying project management and we would like to manually recognize revenues (or at least be able to change it manually).

In the list of activities I have set up the manual accrual method and then I followed the next path: cost and revenue -> sales document item -> I select position to recognize revenue -> Edit Manual revenue recognition Data -> recognized revenue and cost -> introduce values, and after "execute revenue recognition"

The project is selling services to customers, we have actual hours introduced for resources and billed ... When I run revenue recognition I got the information regarding a document created, but no revenue have been posted and I reports do not show any figure.

Could anyone help me to understand what am I doing wrong? Am I missing something? We want to recognize revenue with a manual amount.

I would appreciate if someone could help me.

Thank you very much in advance.

Kind regards.

2.png (6.2 kB)
1.png (64.8 kB)
Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Jul 18, 2016 at 03:25 PM

    Hi Carlos,

    Now to see the result, Please follow the steps

    Go to Cost & Revenues work center

    Under Periodic Tasks > Revenue Recognition

    Select the Run ID mostly it will be latest one , if you have just created it

    Click on View > Go to Postings tab, here you should see the postings and the relevant Journal Entry ID

    Sample:

    Note: Your manual recognition values are maintained from Valid From: 01.03.2016, so your revenue recognition run should be at least for period 03 or later and not before.

    Please mark the thread as answered/helpful if your query is answered.

    Thanks

    Lokesh Sharma


    sample rr.PNG (35.8 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.