All days are working in factory calendar but still giving warning message.

HI Experts,

I have assigned all days are working in my factory calendar (SCAL) and that calendar assigned to my project profile but still giving warning message as below screen shot.

Thank You,

Best Regards,

Yogesh Acharya

Warning.jpg (162.5 kB)
SCAL.jpg (30.5 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Jul 18, 2016 at 07:51 AM

    Hi Yogesh,

    Have you maintained the FC in OPSA or you are manually entering

    Regards

    Terence

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2016 at 09:26 AM

    Hi,

    Check in t- code SCAL, whether factory calendar has defined for special rule or not.

    Like alternative Saturday is working etc......

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2016 at 09:54 AM

    hi ,

    Can you please change the Start date to 0 and this should work

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.