0 Kudos

We have quota for XXXX vendor currently but our end user person would have make PR without source list vendor

How possible is this?

Could you please explain the way?

Accepted Solutions (1)

Accepted Solutions (1)

vijay2006ece
Contributor
0 Kudos

Dear Vinoth,

There are some pre-requisites to work with source list.

While creating PR, if user not selected 'source determination' check box and not performed 'Assign source of supply', then source list vendor will not come to PR.

In the material master 'Source List' indicator should be ticked and For the source list vendors, maintain info record and Need to perform 'Source determination' and 'Assign source of supply' at the time of PR creation.

0 Kudos

Dear Vijay Ji,

I understood your answer.

Thanks for support..

Answers (5)

Answers (5)

former_member197616
Active Contributor

Hi, As a matter of fact all these come in the supply source determination when you have many vendors for a material . the order is Quota Outline agreement Source list Info Record This all comes in the source assignment during  PR creation . System checks in the above order to find the right source . In your case If you have a quota for AAAA vendor system will find this vendor AAAAA during the supply source search . If in case you have quota for AAAA vendor and source list for BBBBB vendor , in the automatic supply source determnation system will have to take the AAAA only . Pre condition is AAAAA quota should be valid . How ever system will allow to change the determined source in the PR . In your case user would have changed the vendor manually or the quota would have been expired . Regards,

former_member183349
Active Participant
0 Kudos

Hi Vinoth,

If there is neither a quota arrangement nor a source list, By default system search for valid outline

agreement items and info records. Therefore you can assign valid outline agreement item or info record

directly. So that there will be either one valid contract or one valid info record.

Kindly note : Outline agreement items have a highest priority than info records in the process.

Thanks,

Vivek

0 Kudos

Thank you vivek ji. while make a new outline agreement for one material , system would create a new quota and source list based on contract validity. but our case is entirely different.

contract, Quota 100% and source list validity is avail for AAAA vendor but PR has been created for BBBB vendor. BBBB vendor also have valid contract. could you explain these case studies..

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

Create contract(ME31K)

Create PR* from Contract(ME51N)

Create PO from PR*(ME21N)

Regards,

Biju K

schaganti1
Contributor
0 Kudos

Remove source list button in MMR in purchasing tab as shown in the below fig

Regards

Sudhakar

Former Member
0 Kudos

HI,

you can remove source list indicator check from material master.

as i understand your question that you want to create PR while source list maintained.

Mukesh