IE02 - change plant

Hi masters

Please, I need to change the planning plant in the IE02 transaction, but the field is locked, is there any other way to do it ? or to unlock the field ?

Is there any mass processing to change it ?

Capturar.PNG (24.9 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    Posted on Jul 21, 2016 at 06:58 AM

    Hi Michel,

    Hope You have got the answer , As I explained all answer will be same.

    Thanks

    Regards

    Gaurav Solanki

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 15, 2016 at 08:22 PM

    Michel

    Use spro tcode OIAF. Here the setting for the field ITOB-IWERK presently must be in Disp. You change it to Input . Now the field will be open for change.

    Good luck

    KJogeswaraRao


    Capture.JPG (58.1 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 16, 2016 at 05:36 AM

    Hi michel,

    First ensure that the screenshot you attached above belongs to IA02 not IE02. According to your screenshot If you want to change planning plant in existing task list then its not possible to change it.

    Now you have to change planning plant in equipment master and for this you will have to go through Rao sir post.Then add or create new task list , you will get new planning plant .

    Thanks

    Regards

    Gaurav Solanki

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 16, 2016 at 05:37 AM

    Michel,

    JRK Sir's answer meets your requirement. But can I ask why you have shared screenshot of Equipment task list?

    Regards,

    Pavan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 18, 2016 at 01:34 PM

    I am sorry.. it is for IA02.

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Michel,

      You can change the planning plant in IE02, there is no harm, but with respect to Equipment task list, you cannot change the planning plant, as said by Pavan, it copies from Equipment Master.

      Only option you have is to delete / archive the task list and create with new plant.

      Regards

      Terence

  • Posted on Jul 21, 2016 at 04:28 AM

    Hi,

    You cant change planning plant in Existing Equipment Task list. To Populate required Planning plant,

    1-You have to change the same Pln Plnt in Equipment Master IE02.

    2-Change same equipment Task List IA02, On header Level Create New Task List.

    3-Go to Task List overview Level and prepare Task List

    4-Select task List Item with Previous Planning Plant and Delete.

    Regards,

    Rakesh


    pastedImage_0.png (11.0 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.