Please, I need to change the planning plant in the IE02 transaction, but the field is locked, is there any other way to do it ? or to unlock the field ?

Is there any mass processing to change it ?

Accepted Solutions (1)

Accepted Solutions (1)

gaurav_solanki2
Participant

Hi Michel,

Hope You have got the answer , As I explained all answer will be same.

Thanks

Regards

Gaurav Solanki

Answers (5)

Answers (5)

rakesh_kushwaha
Participant
0 Kudos

Hi,

You cant change planning plant in Existing Equipment Task list. To Populate required Planning plant,

1-You have to change the same Pln Plnt in Equipment Master IE02.

2-Change same equipment Task List IA02, On header Level Create New Task List.

3-Go to Task List overview Level and prepare Task List

4-Select task List Item with Previous Planning Plant and Delete.

Regards,

Rakesh

Former Member
0 Kudos

I am sorry.. it is for IA02.

pavan_kumarcs
Active Participant
0 Kudos

Michel,

I think planning plant is populated from Equipment Master, it will not allow you to change in IA02.

Regards,

Pavan

MTerence
Active Contributor
0 Kudos

Hi Michel,

You can change the planning plant in IE02, there is no harm, but with respect to Equipment task list, you cannot change the planning plant, as said by Pavan, it copies from Equipment Master.

Only option you have is to delete / archive the task list and create with new plant.

Regards

Terence

pavan_kumarcs
Active Participant
0 Kudos

Michel,

JRK Sir's answer meets your requirement. But can I ask why you have shared screenshot of Equipment task list?

Regards,

Pavan

gaurav_solanki2
Participant
0 Kudos

Hi michel,

First ensure that the screenshot you attached above belongs to IA02 not IE02. According to your screenshot If you want to change planning plant in existing task list then its not possible to change it.

Now you have to change planning plant in equipment master and for this you will have to go through Rao sir post.Then add or create new task list , you will get new planning plant .

Thanks

Regards

Gaurav Solanki

jogeswararao_kavala
Active Contributor
0 Kudos

Michel

Use spro tcode OIAF. Here the setting for the field ITOB-IWERK presently must be in Disp. You change it to Input .  Now the field will be open for change.